LCS reconstruction to begin after sixth supplemental agreement signed: navy chief

Contract prepared by Defence Ministry would see several amendments

Updated 3 years ago · Published on 27 Apr 2023 2:05PM

LCS reconstruction to begin after sixth supplemental agreement signed: navy chief
The littoral combat ships controversy came to a head when the National Accounts Committee revealed that none of the ships had been completed even though the government had paid RM6.083 billion to Boustead Naval Shipyard Sdn Bhd. – Hishammuddin Hussein Facebook pic, April 27, 2023

LUMUT – The project on the reconstruction of the littoral combat ships (LCS) is expected to begin three months after the sixth supplemental agreement is concluded, said Navy chief Admiral Datuk Abdul Rahman Ayob.

Rahman said the contract which is being prepared by the Defence Ministry would see several amendments to the timeline and costs.

“As we are aware, the cabinet meeting held on April 19 had agreed to continue the LCS project. This is an important decision to proceed further.

“If the agreement (contract) is finalised, we hope that the LCS project will be able to commence as early as possible,” he told a press conference after officiating at the Royal Malaysian Navy (RMN) ceremonial parade at Lumut RMN base here today.

Earlier, Defence Minister Datuk Seri Mohamad Hasan said the LCS project will proceed and the first ship is expected to operate in 2026.

The LCS controversy came to a head when the National Accounts Committee revealed that none of the ships had been completed even though the government had paid RM6.083 billion to Boustead Naval Shipyard Sdn Bhd.

Meanwhile, Rahman said the supplemental agreement is expected to be finalised and signed at the Maritime and Aerospace Exhibition 2023 in Langkawi scheduled to take place from May 23 until May 27.

On the littoral mission ship (LMS) project, he said the priority is now on asset acquisition to replace the obsolete RMN vessels.

“At the moment, the main focus is procurement of LMS Batch 2 as approved in the 2023 Budget.

“The assets received from the first batch did not meet the standards, we expect the second batch to have better combat capabilities and we hope the procurement process will be finalised soon,” he said. – Bernama, April 27, 2023

Related News

Malaysia / 2y

Major defence boost for Sarawak to face new challenges

Malaysia / 2y

Procurement cartel: Khaled Nordin vows Mindef’s cooperation with MACC

Malaysia / 2y

MAF ready to serve as peacekeeping force in Palestine if called: Mohamad

Malaysia / 2y

PAC to table report on LCS next month

Malaysia / 3y

LCS project set to resume next month, first ship expected at end-2026: navy

Malaysia / 3y

Defence Ministry will not tolerate any border intrusions: deputy minister

Spotlight

Malaysia

Jokes that hit below the belt: In the race for Malay votes, how far is UMNO willing to go?

By The Vibes Says

Malaysia

UMNO man says he’s prepared to apologise over ‘joke’

Malaysia

Loke proposes PH presidential council meet on ‘latest political developments’

Malaysia

Sabah leaders condemn priest and nun joke at UMNO PAU

Malaysia

DKU affirms that Tuanku Muhriz is the Yang di-Pertuan Besar of Negeri Sembilan

Business

Budget 2027 nears final stage with high-impact sectors in focus

Health

Respiratory disease ranks among Malaysia’s top three health burdens

Malaysia

High Court acquits student in Bandar Utama murder case on schizophrenia finding

Malaysia

PAS rejects UMNO call to test political ties through SG4 polls

You may be interested

Malaysia

High Court acquits student in Bandar Utama murder case on schizophrenia finding

Malaysia

Elderly driver allegedly presses accelerator, hits three people while parking

Malaysia

Police fire at tyres after couple allegedly rams officer, URB motorcycle in Kulai

Malaysia

Former minister to face MACC charges tomorrow

By Alfian Z.M. Tahir

Malaysia

Catholic Lawyers' Society condemns UMNO leader's derogatory remarks

Malaysia

MOH turns to four agencies to keep healthcare services running in Sarawak interior

By Alfian Z.M. Tahir

Malaysia

Minister warns against emotion-driven politics amid UMNO exit calls

Malaysia

Nepal flood disaster: 19 days on, hope still lives