Malaysia

Dhaya Maju LTAT to continue RM4.5 bil KVDT2 project: senior federal counsel

Contract cost, terms, to stay as agreed in letter of acceptance, says Asliza Ali

Updated 4 years ago · Published on 13 Jun 2022 7:32PM

Dhaya Maju LTAT to continue RM4.5 bil KVDT2 project: senior federal counsel
The decision today follows the suit filed on October 27, 2020 by Dhaya Maju LTAT against the government, Datuk Seri Wee Ka Siong, Opus Consultants (M) Sdn Bhd, and Keretapi Tanah Melayu Bhd as respondents over the termination of the company’s contract in the KVDT2 project. – Bernama pic, June 13, 2022

KUALA LUMPUR – The high court was today told that the government had decided to allow Dhaya Maju LTAT Sdn Bhd to continue with the Klang Valley Double Tracking Phase 2 (KVDT2) project.

Senior federal counsel Asliza Ali said the matter was decided during the cabinet meeting on May 18.

Asliza, who was representing the government and Transport Minister Datuk Seri Wee Ka Siong in a suit, made the announcement during online case management before justice Datuk Lim Chong Fong today.

“The KVDT2 project will be continued by Dhaya Maju LTAT with the contract cost of RM4.475 billion, as well as the implementation terms, staying as agreed in the letter of acceptance dated August 19, 2019,” she said when contacted today.

In this regard, Asliza said both parties in the suit had also reached an agreement to settle the suit.

“The plaintiff (Dhaya Maju LTAT) will withdraw its suit after the contract is signed by both parties (government and Dhaya Maju LTAT).

“The court sets June 30 for the parties to announce the development of the settlement of the suit,” she said.

On October 27, 2020, Dhaya Maju LTAT filed a suit against the government, Wee, Opus Consultants (M) Sdn Bhd, and Keretapi Tanah Melayu Bhd as respondents over the termination of the company’s contract in the KVDT2 project.

Based on the statement of claims, Dhaya Maju LTAT, among others, alleged that to date, the official notice of termination had not been issued to the company and it was not aware of the termination until it was announced by Wee in a media statement.

Apart from compensations, Dhaya Maju LTAT, a joint-venture between Dhaya Maju Infrastructure (Asia) Sdn Bhd and Lembaga Tabung Angkatan Tentera, which was incorporated on June 5, 2017 under the Companies Act 2016, sought the declaration of the contract termination to be null and void.

The dispute arose after Finance Minister Datuk Seri Tengku Zafrul Tengku Abdul Aziz issued a list of 101 projects valued at RM6.61 billion awarded via direct negotiation during the Pakatan Harapan administration, including the KVDT2 project valued at RM4.475 billion awarded to Dhaya Maju LTAT. – Bernama, June 13, 2022

Related News

Malaysia / 4y

[UPDATED] My efforts were worth it, says Loke on govt’s resumption of KVDT2

Malaysia / 4y

Dhaya Maju, govt reach out of court settlement over KVDT2 project

Business / 4y

Govt, Dhaya Maju close to settlement on KVDT2 cases, Federal Court hears

Business / 5y

Dhaya Maju gets ad interim injunction on KVDT2 stop-work order until July 26

Malaysia / 5y

Dhaya Maju LTAT withdraws 1 of 2 KVDT2 suits against govt, Wee

Malaysia / 5y

Putrajaya’s appeal against judicial review into nixed KVDT2 fixed for June 16

Spotlight

Opinion

Can Najib break Madani?

World

Trump offers UFC CEO the position of Press Secretary

Malaysia

Building a great nation begins with happy families, says Anwar

Malaysia

Anwar should sack BN ministers who are not aligned with him – Muhyiddin

Malaysia

AGC rejects claims of defying King’s decree on Najib

Malaysia

Deepavali: Selangor Sultan calls on Malaysians to strengthen unity, reject hatred

Malaysia

If there were still obstacles, why accept the RM50m payment, asks Najib’s daughter

Malaysia

Where did UMNO's RM50 million payment for Najib's release come from?

By The Vibes Says

You may be interested

Malaysia

Two killed, three injured as Mercedes catches fire after crash in Johor Bahru

Malaysia

PH Melaka seeks early voter support for federal government's policy direction

Malaysia

Two brothers among three killed by lightning after seeking shelter under tree in Sepang

Malaysia

Four arrested over firecrackers set off in middle of Skudai road

Malaysia

Why PM Anwar’s Waze ban is more than just a traffic move

Malaysia

Anwar comforts crying child, gives RM50 to replace broken toy car (video)

Malaysia

Android TV boxes may be compromised before reaching consumers, NACSA warns

Malaysia

PM announces additional aid of RM2,500 for each flood victim in Selangor