Baling floods: temporary bridge at Kg Iboi ready for use tomorrow

Construction did not involve any cost, says Works Ministry sec-gen

Updated 4 years ago · Published on 08 Jul 2022 12:22PM

Baling floods: temporary bridge at Kg Iboi ready for use tomorrow
Works Ministry secretary -general Datuk Wan Ahmad Uzir Wan Sulaiman says the 90-ft-long and 18-ft-wide temporary bridge in Kg Iboi in Baling could accommodate loads of up to five tonnes. – Bernama pic, July 8, 2022

BALING – The temporary bridge being built in Kg Iboi here to replace the bridge that collapsed in the floods and water surge phenomenon last Monday is expected to be ready for use tomorrow.

Works Ministry secretary -general Datuk Wan Ahmad Uzir Wan Sulaiman said installation of the steel “Old Bailey Bridge” began yesterday by 20 staff from the Road Division and Mechanical Works Branch of the Kedah Public Works Department (JKR) and assisted by 10 members of the Malaysian Armed Forces (ATM).

“Residents have requested us to complete the temporary bridge as soon as possible before Aidiladha so that they can make preparations to celebrate the festival,” he said when contacted here today.

He said the 90-ft-long and 18-ft-wide bridge could accommodate loads of up to five tonnes.

All the heavy machinery materials used in building the bridge belonged to or were obtained from the JKR store. Therefore, its construction did not involve any cost, he said.

Meanwhile, Kg Iboi Development and Security Committee chairman Abu Hasan Samah, 62, said the construction of the temporary bridge would facilitate the daily affairs of about 3,000 residents from several villages in the area.

He said the bridge, which collapsed last Monday, served as a link for residents from Kg Masjid Iboi, Kg Bok Bak, Kg Tanjung Luas and Kg Tanjung Nering to go to the town, and since then, they were forced to take the longer route.

"Residents in Kg Iboi also use the bridge to go to the mosque across the river, and we are indeed grateful to the government for providing us with the temporary bridge and hope it will be ready soon,” he added. – Bernama, July 8, 2022

Related News

Malaysia / 3y

17 Kg Iboi yellow zone families to get new homes: Sanusi

Malaysia / 3y

Environment Ministry to let Kedah decide on Gunung Inas reservoirs

Malaysia / 3y

Baling floods saw losses of around RM28 mil: Sanusi

Malaysia / 4y

Baling floods: one evacuation centre closes, 94 victims still sheltering at another

Malaysia / 4y

Man braves Baling floodwater to save siblings, neighbour

Malaysia / 4y

Baling flood returns, 130 victims evacuated to relief centres

Spotlight

Malaysia

Documents reveal British royal charity attempted to ‘doctor’ evidence in SLAPP action

Malaysia

MMA asks why FDS aircraft cannot match those used by ministers

Malaysia

Penang-born woman dies in Perth after alleged domestic violence assault

Malaysia

No senior UMNO leaders to be arrested after PAU – MACC

Malaysia

Hng’s 31-year Gerakan exit puts focus on political direction

By Alfian Z.M. Tahir

Malaysia

Man held after social media claim he solicited alms while carrying parang

Malaysia

Volcanic escalation on Java a threat of potential regional chaos

Malaysia

Anwar surprised by Najib's new pardon attempt

You may be interested

Malaysia

Volcanic escalation on Java a threat of potential regional chaos

Malaysia

Fahmi: 65,280 scam, illegal gambling posts still online despite MCMC takedown requests

Malaysia

Four Chinese nationals charged with kidnapping Singaporean for ransom

Malaysia

‘We need more healthcare professionals, not corrupt politicians’

Malaysia

Property market holds firm with RM105.1b transactions in 1H2026

Malaysia

Hng’s 31-year Gerakan exit puts focus on political direction

By Alfian Z.M. Tahir

Malaysia

Penang-born woman dies in Perth after alleged domestic violence assault

Malaysia

Fadillah returns to Cabinet after heart bypass surgery