Phase one of Sarawak Pan Borneo Highway 86% complete: Fadillah

Several more sections expected to be opened this year, says minister

Updated 4 years ago · Published on 04 Sep 2022 9:10AM

Phase one of Sarawak Pan Borneo Highway 86% complete: Fadillah
Public Works Minister Datuk Seri Fadillah Yusof says another three sections of the Pan Borneo Highway in Sarikei, Bukit Begunan and Lambir are facing various challenges including a site that needs to be re-examined. – Bernama pic, September 4, 2022

KUCHING – Phase one of the Pan Borneo Highway project in Sarawak is now 86% complete, according to Public Works Minister Datuk Seri Fadillah Yusof.

He said several more sections of the highway are expected to be opened this year and three other sections in Sarikei, Bukit Begunan and Lambir are expected to be completed next year.

“The three sections are facing various challenges including a site that needs to be re-examined.

“There are even some that require reprocessing of the design due to the unsuitable terrain conditions,” he told reporters after attending the Sarawak Media Engagement programme here last night.

Phase one of the RM16.117 billion Pan Borneo Highway project involves the construction of a 786km stretch of road from Telok Melano to Miri.

Meanwhile, Fadillah said the Finance Ministry is also currently finalising the procurement aspect for the Sarawak-Sabah Link Road (SSLR) Phase 2 Project and the Trans Borneo Highway (LTB) Project and a ceiling allocation of RM12 billion has been set for both projects.

“We also hope to be able to finalise the awarding of contracts to contractors this year and by early next year this project will be able to start,” he said.

On August 7, Prime Minister Datuk Seri Ismail Sabri Yaakob said the federal government had approved the SSLR Phase 2 Project and the LTB Project, and construction would commence as early as next year.

Ismail Sabri said technical research for the Phase 2 SSLR and LTB project connecting Miri, Limbang and Lawas is now in the final stage, with construction expected to take three to five years.

The prime minister also said that the project would not only allow residents of northern Sarawak to reach Sabah through two road network options but also benefit residents in Mulu, Long Seridan, Nanga Medamit, Long Lopeng, Ba’kelalan and Merarap who currently rely on logging roads to commute. – Bernama, September 4, 2022

Related News

Malaysia / 1d

Abang Johari hints four incumbents will be retained for Sarawak polls

Malaysia / 1w

Sarawak’s snap polls: A clean sweep for Abang Jo’s GPS?

Education / 1w

Schools to get extra holidays for Deepavali

Malaysia / 1w

Election Commission to meet on Nov 6 to set key dates for Sarawak polls

Malaysia / 2w

Sarawak PRN: PAS almost certain of contesting in 3 DUNs

Malaysia / 2w

Abang Johari urges parties to respect law as Sarawak heads for polls

Spotlight

Opinion

Can Najib break Madani?

World

Trump offers UFC CEO the position of Press Secretary

Malaysia

Building a great nation begins with happy families, says Anwar

Malaysia

Anwar should sack BN ministers who are not aligned with him – Muhyiddin

Malaysia

AGC rejects claims of defying King’s decree on Najib

Malaysia

Deepavali: Selangor Sultan calls on Malaysians to strengthen unity, reject hatred

Malaysia

If there were still obstacles, why accept the RM50m payment, asks Najib’s daughter

Malaysia

Where did UMNO's RM50 million payment for Najib's release come from?

By The Vibes Says

You may be interested

Malaysia

The question remains: Who paid Najib's RM50m fine?

Malaysia

Man dies after suspected fall from 23rd floor of Penang hotel

By Ian McIntyre

Malaysia

Four arrested over firecrackers set off in middle of Skudai road

Malaysia

Anwar comforts crying child, gives RM50 to replace broken toy car (video)

Malaysia

17-year-old girl found dead near Putrajaya multi-storey car park

Malaysia

Malaysia must reduce reliance on foreign workers through automation, robotics, says Johari

Malaysia

PH intensifies voter outreach in 15 Melaka seats as polling day nears

Malaysia

PM announces additional aid of RM2,500 for each flood victim in Selangor