‘No appointment docs for firm procuring ventilators caused govt to lose millions’

A-G’s Report 2021 reveals 108 of 136 devices supplied by Pharmaniaga defective

Updated 3 years ago · Published on 17 Feb 2023 7:00AM

‘No appointment docs for firm procuring ventilators caused govt to lose millions’
The Auditor-General’s Report 2021 states that the lack of appointment documents between Pharmaniaga Logistics Sdn Bhd and the Health Ministry on the procurement of ventilators means the government cannot seek compensation over the faulty ventilators supplied. – SYEDA IMRAN/The Vibes file pic, February 17, 2023

by Qistina Nadia Dzulqarnain

KUALA LUMPUR – The lack of documentation surrounding the appointment of Pharmaniaga Logistics Sdn Bhd to procure ventilators for the Health Ministry during the Covid-19 pandemic cost the government a whopping RM13.07 million. 

This is according to the Auditor-General’s Report 2021 published yesterday, which revealed that out of the 136 ventilators supplied by the company in 2020 for RM24.07 million, only 28 were usable while the rest were “unsafe” for patients. 

Of the 108 malfunctioning ventilators, 15 were returned to their factories overseas for replacements while the other 93 failed performance and quantitative tests executed on them.

“The government cannot seek compensation claims (for the faulty ventilators) as there are no appointment documents between (Pharmaniaga Logistics) and the Health Ministry on ventilator procurements. 

The amount of loss suffered over the 93 unusable ventilators is estimated to be around RM13.07 million,” the report said. 

It noted the ministry’s claims the procurements were done as part of the company’s corporate social responsibility. 

The Auditor-General’s Report 2021 notes the Health Ministry’s claims that the procurements of ventilators from Pharmaniaga Logistics Sdn Bhd, a subsidiary of Pharmaniaga Bhd, were done as part of the company’s corporate social responsibility. – Pharmaniaga Bhd Facebook pic, February 17, 2023
The Auditor-General’s Report 2021 notes the Health Ministry’s claims that the procurements of ventilators from Pharmaniaga Logistics Sdn Bhd, a subsidiary of Pharmaniaga Bhd, were done as part of the company’s corporate social responsibility. – Pharmaniaga Bhd Facebook pic, February 17, 2023

The report detailed that the ministry had originally approved an early payment of RM30 million to the company to secure 500 ventilators, with the total cost of the deal expected to be around RM50 million. 

While Pharmaniaga Logistics had then returned RM6.97 million of the initial payment on June 18, 2020, it was agreed at a price negotiation meeting on September 1 of the same year that RM3.97 million be channelled to the company for “upgrading works”, the report said.

This came about after it was discovered that 108 ventilators were not functioning properly.

Based on feedback from the Health Ministry, the evaluation for the ventilator procurement was done based on brochures and catalogues from manufacturers as country borders were closed then, which limited movement activities.

“As such, confirmation on the specifications of purchased ventilators could only be done when the machines arrived at the health facility,” the report said. 

It added that no documents regarding dealings on such procurements were provided during the auditing process. 

It noted that this hindered the auditor-general’s ability to determine the role and responsibilities of the company as the party that handled the purchasing and dealt with suppliers. 

According to the Auditor-General’s Report 2021, of the 108 malfunctioning ventilators supplied by Pharmaniaga Logistics Sdn Bhd, 15 were returned to their factories overseas for replacements while the other 93 failed performance and quantitative tests executed on them (pic for illustration purposes only). – AFP pic, February 17, 2023
According to the Auditor-General’s Report 2021, of the 108 malfunctioning ventilators supplied by Pharmaniaga Logistics Sdn Bhd, 15 were returned to their factories overseas for replacements while the other 93 failed performance and quantitative tests executed on them (pic for illustration purposes only). – AFP pic, February 17, 2023

According to a response from the ministry dated October 7 last year, a start-work order was issued to Pharmaniaga Logistics by the ministry’s Medical Development Division on September 2, 2020 based on the price negotiation meeting the previous day. 

“No agreement was signed since the purchase was conducted as an ‘emergency procurement’ and the need to have an agreement was not specified in the Treasury Plan 3.3.

“The ministry has also agreed to the company’s offer to provide 18 replacement ventilators based on the cost of the remaining 93 units which will be sent to the Technical Training Centre for skill upgrading,” the ministry said, as quoted in the report. 

It was previously reported that the ministry had carried out emergency procurement to ensure the needs of frontliners were adequate since the outbreak of Covid-19 in the country.

Guidelines and procedures under Treasury Plan 3.3, namely the Emergency Expenditure Guidelines (AP55) and Emergency Procurement (173.2) were utilised for the purpose. – The Vibes, February 17, 2023 

Related News

Malaysia / 1y

143 taken ill after odour pollution, says health minister

Malaysia / 2y

Enough insulin to last until year end, says health minister

Malaysia / 2y

Health authorities seize illegal sex stimulants in nationwide raids

Malaysia / 2y

Think tank urges establishment of health security agency

Malaysia / 2y

Govt to address AstraZeneca vaccine worries this week

Malaysia / 2y

Address growing nurse vacancies at public hospitals, MCA veep tells MoH

Spotlight

Opinion

“I’m not a war criminal, I’m a patriot”: Shavendra Silva’s amnesia tour meets the receipts

By Abbi Kanthasamy

Malaysia

British management on trial – does a royal management institute deliver value?

Malaysia

Doctor among five killed in Sarawak Flying Doctor helicopter crash identified

Malaysia

Nearly 10,000 potential fire hotspots detected on RSPO-managed land

Malaysia

Undang Yang Empat produces letter allegedly confirming Tuanku Muhriz’s removal

Malaysia

Northern Malaysia must prepare for the consequences of lower rainfall

Malaysia

Helicopter crashes during flying doctor service mission in Sarawak

You may be interested

Malaysia

RM2.41b drug seizure uncovers massive Puncak Alam lab

Malaysia

Jamil Khir released after seven-day remand in Tabung Haji RCI probe

Malaysia

The potential for a redevelopment of Port Dickson

Malaysia

Plot to topple government: Probe not only Hadi, but Takiyuddin and Samsuri also, says Rayer

By Ian McIntyre

Malaysia

Helicopter crashes during flying doctor service mission in Sarawak

Malaysia

Jokowi calls on global institutions to meet  needs growing, interconnected world

By Ian McIntyre

Malaysia

Proclamation to remove Tuanku Muhriz invalid, says Undang

By Alfian Z.M. Tahir

Malaysia

PH warns BN it is ready to go it alone as uncertainty rises in Melaka