First phase of Penang’s Bukit Kukus highway to open on Jan 13

Delayed by landslide, Covid-19 lockdowns, technical issues, project finally sees completion

Updated 4 years ago · Published on 05 Jan 2022 2:02PM

First phase of Penang’s Bukit Kukus highway to open on Jan 13
Penang Chief Minister Chow Kon Yeow and his delegation inspecting the newly completed stretch of highway – IAN MCINTYRE/The Vibes pic, January 5, 2022

by Ian McIntyre

BALIK PULAU – The much-awaited first phase of the Bukit Kukus highway is set to open to motorists on January 13, following a nine-month delay.

The first major highway to be completed under the DAP-led state government since 2008 is supposed to reduce traffic congestion in the area by up to 30%.

Completed this week, the highway marks a major achievement for the state, as it suffered numerous delays following a major landslide in 2018 which claimed nine lives, Covid-19 lockdowns as well as technical issues.

Chief Minister Chow Kon Yeow visited the site today along with Penang Island City Council (MBPP) president Datuk Yew Tung Seang, state exco for infrastructure Zairil Khir Johari and MBPP secretary A. Rajendran.

The council is the developer of the first phase of the highway.

The completed section of the Bukit Kukus paired road, which links Paya Terubong to Bukit Jambul (one of the hilly areas in the Balik Pulau district), is now ready to accept traffic by next week.

Zairil said MBPP had already completed its portion of the construction work recently.

“It has been delayed a few times due to the landslide, the Covid-19 lockdown and some technical issues involving additional work, but it is now ready.”

Constructed at a height of 55m from its pile caps, Zairil said that the stretch is the highest elevated highway in the country, and it also represents the state’s legacy for residents here in its goal to alleviate congestion.

The highway is designed to divert the converging traffic from Balik Pulau and Paya Terubong to Bukit Jambul, which is crucial especially during rush hour.

The 5.5km paired road project, which costs RM545.6 million, consists of three sections.

It primarily connects Paya Terubong and Relau through Bukit Jambul.

The state, through MBPP, is responsible for the construction of a 3.3-km stretch, which has since been completed from Paya Terubong to Relau and Bukit Jambul.

The other two stretches under PLB Land Sdn Bhd and Geo Valley Sdn Bhd are for the remaining 1.4km (RM150 million) and 0.8km (RM120 million), respectively.

PLB’s stretch should be ready by 2025 whereas the Geo Valley one is on hold due to a court case which is believed to be linked to the landslide incident. – The Vibes, January 5, 2022

Related News

Events / 5d

Penang launches sharing integrative platform to reduce shortage in key high-skilled areas

Community / 5d

Penang Mutiara LRT can be expanded if there is a need – MRT Corp

Malaysia / 5d

18 vehicles damaged after being hit by drug-positive driver

Malaysia / 6d

4WD driver who drove backwards on highway nabbed, positive for drugs (video)

Events / 6d

Glamparents Showtime 2026 raises over RM71,000 for charity

Malaysia / 6d

‘Get your facts right’ – says CM over claims that Penang is going bankrupt

Spotlight

Malaysia

PM Anwar – ‘Rather a torn shirt, than …’ (video)

By Alfian Z.M. Tahir

Malaysia

After years of abandonment, Highland Towers to be demolished before year end

Malaysia

PH seat distribution finalised, PKR to contest 20 Johor PRN seats, 16 in Negeri

Malaysia

Rosmah Mansor denies viral allegations, lodges police report

Malaysia

Four arrested after maid abuse footage exposes alleged pattern of domestic worker mistreatment

Malaysia

Muhyiddin's 'congratulatory' message to Hamzah a fake

Malaysia

Hamzah Zainudin launches new political party, Parti Wawasan Negara

Malaysia

Disturbing video of alleged employers assaulting their helper goes viral (video)

You may be interested

Malaysia

Rosmah Mansor denies viral allegations, lodges police report

Malaysia

Rohingya motorcyclist with 34 outstanding summonses detained after attempted escape from JPJ

Malaysia

Lee’s resignation from PKR leadership questioned, labelled as betrayal of mandate

By Alfian Z.M. Tahir

Malaysia

Women are pillars of national progress, community formation - PM Anwar

Malaysia

Johor MB questions federal engagement as KTM Komuter launch invitation remains outstanding

Malaysia

Loke shrugs off Onn Hafiz's snub, lists Johor’s presence at transport events

By Alfian Z.M. Tahir

Malaysia

PAS president accused of bypassing PN leadership as internal power dynamics come under scrutiny

Malaysia

Selangor still Malaysia’s top economic engine, DOSM data counters political claims

By Alfian Z.M. Tahir