Labuan contractors facing building materials shortages, govt projects at standstill

Change in export policy, closure of quarries due to Covid-19 driving angst among contractors

Updated 4 years ago · Published on 10 Nov 2021 3:48PM

Labuan contractors facing building materials shortages, govt projects at standstill
The Labuan G1 Contractor Association says that building material importers now must use the K2 form – instead of the K3 form previously – and approval process is causing delays. – The Vibes file pic, November 10, 2021

LABUAN – Contractors across this duty-free island are struggling to take advantage of the reopening of the economy, as rising costs and the lack of building materials are threatening their business operations.

Local contractors here lamented that the increasing cost of building materials due to supply shortages is the biggest concern for their project management plans.

Labuan G1 Contractor Association president Chemat Mustapha said the lack of availability of building materials such as cement and stones was due to the recent review of export policy from Sabah and the closure of quarries due to the Covid-19 pandemic on the mainland.

“On the issue of stone supply, the Sabah Government needs a permit (issued by the Ministry of Energy and Natural Resources) from the main supplier before the supply is permitted to be exported to Labuan… the issuance of the permit takes time and (this) causes the delay in supply to Labuan,” he told Bernama.

Chemat said the new stone export policy to Labuan took effect in October this year.

“Prior to the review, Labuan importers (building materials companies) are using the K3 customs declaration form (Transportation of Goods Between Peninsular Malaysia, Sabah and Sarawak and transportation within the same territory).

“But now (effective October), they are required to use the K2 form – for export of goods from the country, of which the process of approval takes time… many government projects come to a standstill due to this delay,” he said.

Chemat also urged the Public Works Department to review the price of the project tender to account for the rising cost of building materials.

A local contractor, Sophian Said, said the unavailability of these building materials had caused his company’s projects to come to a standstill.

“The price of raw materials is rising dramatically, and traditional fixed-price contracts are not designed to account for this new reality,” he said.

Sophian said this trend is expected to continue until next year and would impact not only cost but also lead times, which subsequently would cause project delays and a difficulty in meeting scheduled requirements. – Bernama, November 10, 2021

Related News

Malaysia / 3w

Three new projects expected to spark greater growth in Penang

Malaysia / 4w

Tengku Zafrul: ‘PH to continue expanding economic growth in Negeri’

Malaysia / 2mth

King calls for people-centred development in KL

Opinion / 2mth

Langkawi: An untapped island with much greater potential?

Off beat / 2mth

Penang: CM orders all state excos to monitor development progress

Malaysia / 2mth

Najib’s son joins protestors against high-rise development in Langkawi

Spotlight

Malaysia

Tuanku Muhriz urges Malaysians to uphold Rukun Negara, strengthen unity

Malaysia

PM to bring Felda forensic audit proposal to Cabinet

Malaysia

Malaysia tightens Thailand border security after wave of southern attacks

Malaysia

Mohd Amar’s three-year remark puts PAS’ Kelantan record under spotlight

Malaysia

KPF’s Al-Rawda exposure raises fresh questions over RM119.38 million

By Alfian Z.M. Tahir

Trump’s North Korea gamble deepens Asia’s doubts over US alliances

Malaysia

Rayer denies involvement in 'Maha Kali Red Rally', claims name and photo misused

Business

Nation’s economic outlook strengthens as leading index signals continued growth

You may be interested

Business

Nation’s economic outlook strengthens as leading index signals continued growth

Business

Oil prices pull back after rally as markets brace for tougher Iran sanctions

Business

Matrix Concepts records RM416.7m in 1Q27 sales as geographic diversification gains traction

Business

Oil prices hold near US$85 as US-Iran tensions keep hormuz risks in focus

Business

K8 cargo: Businessman seeks clarification from MOF, Customs, Petronas