Terminating contractors in delayed projects to be last resort: deputy minister

Datuk Arthur Joseph Kurup says time extension, variation of prices will be allowed first

Updated 4 years ago · Published on 18 Jul 2022 4:16PM

Terminating contractors in delayed projects to be last resort: deputy minister
Deputy Works Minister Datuk Arthur Joseph Kurup says among the reasons for project delays are the rising prices of building materials, disruption to the supply chain of building materials, manpower shortage due to the implementation of the movement control order since March 2020 and last year’s floods. – Bernama pic, July 18, 2022

KUALA LUMPUR – The government has always taken steps to assist contractors to complete their projects, including allowing them to apply for the implementation of the Variation of Prices (VoP) clause to ensure the survival of contractors affected by rising prices of building materials.

Deputy Works Minister Datuk Arthur Joseph Kurup said the government understands the matter and any move to terminate the contract of contractors involved in delayed projects or “ailing” projects would be the last step taken by the government.

“The government really understands that among the main factors for project delays was the rising building material prices. Besides the allowance of extension of time, the VoP will ensure termination will be the last resort,” he said in the Dewan Rakyat today.

He said this in reply to a supplementary question by Datuk Hasanuddin Mohd Yunus (Hulu Langat-PH) on measures taken by the Works Ministry in helping contractors facing having their services terminated due to delays in the projects carried out by them.

In his reply to the original question by Ahmad Johnie Zawawi (Igan-GPS), Kurup said that as of June 30, a total of 84 projects had been categorised as being delayed projects compared to the 696 government contracts under construction by the Works Ministry, or equivalent to 12%.

He said that apart from rising prices of building materials, other unforeseen factors also contributed to the delays in completing the projects, such as disruption to the supply chain of building materials, manpower shortage due to the implementation of the movement control order since March 2020 and floods in 2021 that also affected private projects.

The government had previously agreed to implement the VoP to ensure government projects were not affected and could be completed according to schedule.

“The conditions and method of calculating the VoP in this work contract are from January 1, 2021 until June 30, 2022. The list of building materials included in this circular is reinforced steel, crusher run, mild steel pipe (water and sewer pipes) and copper.

“To further ease the burden of construction industry players, the prime minister had, on July 14, added 11 more building materials in the implementation of the VoP, bringing the total to 15 approved building materials,” he said. – Bernama, July 18, 2022

Related News

Malaysia / 2w

MP to raise commingled oil cargo tax uncertainty in Parliament

Malaysia / 1mth

Speaker informs EC of Subang parliamentary seat vacancy

Malaysia / 1mth

Tabung Haji RCI report takes centre stage at special Dewan sitting tomorrow

Malaysia / 1mth

No discussions yet regarding general election – Zahid

Malaysia / 1mth

BNPL users hit eight million as outstanding balances reach RM5.3b

Malaysia / 2mth

Speaker reminds MPs not to skip parliamentary sessions

Spotlight

Malaysia

Documents reveal British royal charity attempted to ‘doctor’ evidence in SLAPP action

Malaysia

MMA asks why FDS aircraft cannot match those used by ministers

Malaysia

Penang-born woman dies in Perth after alleged domestic violence assault

Malaysia

No senior UMNO leaders to be arrested after PAU – MACC

Malaysia

Hng’s 31-year Gerakan exit puts focus on political direction

By Alfian Z.M. Tahir

Malaysia

Man held after social media claim he solicited alms while carrying parang

Malaysia

Volcanic escalation on Java a threat of potential regional chaos

Malaysia

Anwar surprised by Najib's new pardon attempt

You may be interested

Malaysia

Pardons Board meeting puts Najib Razak's house arrest bid under scrutiny

Malaysia

Lawyer denies Abdul Azeez chose to appear in lock-up uniform, handcuffs

Malaysia

Volcanic escalation on Java a threat of potential regional chaos

Malaysia

Senior PAS leaders attend UMNO assembly as party ties come back into focus

Malaysia

Man held after social media claim he solicited alms while carrying parang

Malaysia

Najib’s pardon application deferred

By Alfian Z.M. Tahir

Malaysia

PPIM calls for asset seizures, harsher penalties for scam syndicates

Malaysia

Anwar: Sabah, Sarawak to get higher parliamentary representation under MA63