BNS likely to struggle in servicing RM1 bil LCS debts: declassified report

Finance Ministry approved deposit to contractor 136 times more than allowed

Updated 3 years ago · Published on 17 Aug 2022 5:40PM

BNS likely to struggle in servicing RM1 bil LCS debts: declassified report
Boustead Naval Shipyard Sdn Bhd has been mired in controversy since the release of the Public Accounts Committee report on the government procurement of the six littoral combat ships earlier this month, which recommended the Malaysian Anti-Corruption Commission to take prosecutive action against those behind the scandal. – Hishammuddin Hussein Facebook pic, August 17, 2022

by Amar Shah Mohsen

KUALA LUMPUR – Boustead Naval Shipyard Sdn Bhd (BNS), the main contractor for the littoral combat ship (LCS) project, was found to have poor financial capability and performance, and is expected to face serious issues in servicing loans amounting to close to RM1 billion.

This was among the findings made by the Governance, Procurement and Finance Investigation Committee (JKSTUPKK) following its forensic investigation in 2019 into the government’s procurement of six second-generation patrol vessels, its report of which was declassified today.

According to the 106-page long report, BNS was already found to lack the financial prowess to undertake the project since it was awarded the RM9 billion deal by the government on December 16, 2011.

This was underscored by the company’s request for deposit from the government amounting to RM1.8 billion, or 20% of the overall contract value, to kickstart the construction of the vessels.

The report noted that the amount was to pay suppliers and original equipment manufacturers (OEM) for the procurement of RM1.9 billion worth equipment and design and engineering services.

While not granting the full amount, the Finance Ministry had, between December 2011 and January 2014, approved a total of RM1.365 billion (14.95% of overall project cost) in deposit payments to BNS, and offered exemption for bank guarantees for RM836.9 million of the deposit.

Based on the committee’s report, the payments were made on four separate occasions, all of them before BNS and the government signed a formal contract for the LCS project in July 2014, the first of which was made on December 29, 2011, merely two weeks after BNS was issued its letter of award (LOA).

JKSTUPKK found that the RM1.365 billion deposit and bank guarantee exemption were also “beyond the norms” of the Treasury Circular and procurement regime which stipulates that the government shall not provide deposit payments over RM10 million to any local manufacturer or supplier.

“These prove that the company (BNS) has limited financial capability to implement the project,” it said.

According to the committee’s report, an analysis into BNS’ financial statements from 2014 to 2018 discovered that the firm had recorded losses in three of the five years.

The accrued losses had swelled to RM462 million as of 2018, pushing the company into the red with an equity of negative RM332 million then.

JKSTUPKK noted that the financial management and cash flow issues faced by BNS had caused delays in payments to OEMs and suppliers, subsequently resulting in postponements in the delivery of equipment and causing temporary stop on works in the shipyard.

The report further pointed out that in order to address its cash flow issue and to finance the LCS construction, BNS had sought loans from banks and its parent company Boustead Holdings Bhd amounting to RM956.86 million, of which RM354.96 million were short-term loan and RM601.9 million long term.

“Based on debt ratio analysis to measure the total percentage of assets financed by debt, we found the trend quite worrying.

“BNS is expected to face difficulties and inability to pay their debts and interests in the long term if its financial situation remains weak,” it said.

BNS has been mired in controversy since the release of the Public Accounts Committee report on the government procurement of the six LCS earlier this month, which recommended the Malaysian Anti-Corruption Commission to take prosecutive action against those behind the scandal.

So far, former navy chief Tan Sri Ahmad Ramli Mohd Nor, who had previously served as the managing director of BNS, has been charged in court with three counts of criminal breach of trust involving the multi-billion ringgit project. – The Vibes, August 17, 2022

Related News

Malaysia / 2y

PAC to table report on LCS next month

Business / 2y

BHIC unit disposes of 20.77% stake in Boustead Naval Shipyard for RM1

Malaysia / 2y

LCS project set to resume next month, first ship expected at end-2026: navy

Malaysia / 2y

LCS: PAC to visit Lumut naval base, commence proceedings on Saturday

Malaysia / 3y

Transparency International again demands govt explain LCS issues

Malaysia / 3y

MoF has no choice but to take over LCS project: Anwar

Spotlight

Business

Tycoon Vincent Tan trims BCorp stake further in RM115m share sale

Malaysia

UMNO’s solo gamble in Johor: A show of strength or risky miscalculation?

By The Vibes Says

Malaysia

Nik Aziz’s grandson allegedly slapped by senator: Father ready to take case to court

Malaysia

Lorry driver jailed a day, fined for making obscene gestures, dangerous driving (video)

Malaysia

PKR leader defends MyKhas access suspension for PJ, Subang MPs, cites ‘political choices’

Opinion

Social media set to dominate Johor polls as election kingmaker

Malaysia

Man charged in Butterworth parang attack case that left victim fearing permanent disability

Malaysia

Teen mothers must return to school, says Fadhlina as education remains priority

Malaysia

Penang water tariffs to increase from July 1 after year-long deferment

You may be interested

Malaysia

Cops dismantle 3 international fraud syndicates in Penang, arrest 32 suspects

Malaysia

Nik Aziz’s grandson allegedly slapped by senator: Father ready to take case to court

Malaysia

King Sultan Ibrahim urges new MACC chief to uphold highest integrity in fight against corruption

Malaysia

Police looking for trio involved in violent armed robbery in Penang (video)

Malaysia

Police confirm mystery of Jaslinda's disappearance has no criminal element

Malaysia

Fadillah warns of finite fossil fuels, global volatility and rising demand

Malaysia

King calls for people-centred development in KL

Malaysia

MITI: Malaysia rejects forced labour claims as US Section 301 tariff proposal enters consultation phase