Malaysia

LCS delays revive questions over warnings raised by former navy chief

Several supplementary contracts linked to the fleet’s full readiness are only expected to be completed by December 2035, about five years after the main contract ends on April 25, 2030.

Updated 1 month ago · Published on 07 Oct 2026 10:08AM

LCS delays revive questions over warnings raised by former navy chief
The latest audit shows that issues surrounding the LCS programme extend beyond the delays that marked its earlier stages. - October 7, 2026

THE latest audit findings on the littoral combat ship (LCS) programme have renewed scrutiny of warnings raised by former Navy chief Admiral Tan Sri Abdul Aziz Jaafar during the project’s early stages.

The Auditor-General’s Report 2/2026 found that the overall programme was 7.55% behind schedule as at June 25, with delays ranging from 30 to 108 days.

The first LCS, initially scheduled for physical handover on Aug 26, 2026, is now targeted for delivery on Dec 26.

However, the National Audit Department said the ship would not be fully operational if handed over on that date, as training and weapons systems would not yet be complete.

Several supplementary contracts linked to the fleet’s full readiness are only expected to be completed by December 2035, about five years after the main contract ends on April 25, 2030.

The delays could also affect the delivery schedule for LCS 2 to LCS 5, raising questions over when the fleet will achieve the capabilities stipulated under the programme.

The development has brought renewed attention to concerns Abdul Aziz raised over the procurement process.

Records of Public Accounts Committee (PAC) proceedings show that he had written to several senior government officials, including then prime minister Datuk Seri Najib Razak, then defence minister Datuk Seri Ahmad Zahid Hamidi, the Chief Secretary to the Government and the Treasury secretary-general.

Abdul Aziz raised concerns about the Royal Malaysian Navy's (TLDM) position as the end user, saying its views were not given due consideration during the procurement process.

During PAC proceedings, he described the situation as “something is gravely wrong” after the navy’s views were not taken into account in the implementation of the project.

The PAC’s 2022 report found that the government had paid RM6.083 billion for the LCS programme, although none of the ships had been completed according to the original schedule at the time.

The committee also found that the government’s due diligence on Boustead Naval Shipyard (BNS) had failed to identify the company’s financial problems before advance payments of up to RM1.36 billion were made.

The latest audit shows that issues surrounding the LCS programme extend beyond the delays that marked its earlier stages.

Several supplementary contracts remain unfinished as the government works towards the delivery of the first ship.

One is the RM535.37 million Integrated Logistics Support and Trial Aids (ILS-TA) contract.

The National Audit Department said its contract documents had not been formally finalised as at June 25, despite two progress payments totalling RM100 million having been made.

The department recommended that the Defence Ministry draw up a realistic recovery plan and strengthen monitoring by assigning officers to address critical issues and setting deadlines for their resolution.

The LCS programme has now moved well beyond its original delivery timetable, with the latest audit raising fresh concerns over both the completion of supporting contracts and the operational readiness of the ships.

For the government, the immediate task is to ensure that the first vessel is not only handed over, but can eventually operate with the systems, training and support required under the programme. – October 7, 2026

Related News

Malaysia / 1d

'I'm bored with the repeated criticism from Umno' - Tony Pua

Malaysia / 2d

Najib has been given a second chance. But where is the accountability to Malaysians?

Malaysia / 2d

Umno seeks clarification on declassification of Najib's pardon board minutes

Malaysia / 3d

Najib’s house arrest: Govt, AG, Hannah opposed conditional pardon, minutes show

Malaysia / 3d

Padang Rengas dispute exposes challenge facing possible BN-PN pact

Malaysia / 4d

Zahid: One name submitted for new Negeri MB

Spotlight

World

Singaporean extradited to US over alleged global insider trading network

Malaysia

Malaysia will not bow to external pressure in deepening China ties, says Anwar

Opinion

When those entrusted to defend the country are accused of drug smuggling

By The Vibes Says

Malaysia

Palace tells Ismail to prove majority support before new exco appointments

By Alfian Z.M. Tahir

Malaysia

Man who sodomised, killed baby under his care sentenced to death by hanging

Malaysia

Ismail vows to resign if state government breaches undertaking to Tuanku Muhriz

Malaysia

Ismail Lasim to remain as Negeri MB

Heritage

No development at Mount Erskine burial site: land is for cemetery-related purposes

By Ian McIntyre

You may be interested

Malaysia

Palace tells Ismail to prove majority support before new exco appointments

By Alfian Z.M. Tahir

Malaysia

MMA seeks urgent probe into claim Sabah doctor used phone torch during procedure

By Alfian Z.M. Tahir

Malaysia

Umno-PAS ties tested by competing ambitions ahead of GE16

Malaysia

PH challenges BN-PN to produce evidence or retract royal institution allegations

Malaysia

Azmin’s appearance at Amanah convention draws attention

Malaysia

Ismail vows to resign if state government breaches undertaking to Tuanku Muhriz

Malaysia

Prolonged floods take toll on Kuala Selangor evacuees as 1,655 remain in relief centres

Malaysia

Johor steps up anti-bullying drive after 773 cases recorded in nine months