ECRL 30% complete as of May, likely to hit 37% year-end target: Wee

Transport minister adds 23,000-strong labour force needed in peak construction period in 2023

Updated 4 years ago · Published on 23 Jun 2022 6:06PM

ECRL 30% complete as of May, likely to hit 37% year-end target: Wee
Transport Minister Datuk Seri Wee Ka Siong speaks at the opening ceremony of the construction of the Pahang ECRL Genting Tunnel in Bentong today, which was officiated by Prime Minister Datuk Seri Ismail Sabri Yaakob. – Bernama pic, June 23, 2022

BENTONG – Construction work on the East Coast Rail Link (ECRL) project has recorded overall progress of 30% as of May this year, says Transport Minister Datuk Seri Wee Ka Siong.

He said the project was likely to hit the projected 37% completion rate by the end of this year.

The development, he added, was driven by infrastructure work in four states, which included the alignments of Section A from Kota Baru to Dungun, Section B from Dungun to Mentakab and Section C from Mentakab to Port Klang.

According to Wee, the infrastructure work is running simultaneously in sections A, B and C and in more than 300 work areas along the 665-km railway line.

“The number of work areas will continue to increase towards the peak of construction in 2023, where a manpower of 23,000 will be needed to develop the ECRL project more effectively,” he said during his address at the opening ceremony of the construction of the Pahang ECRL Genting Tunnel here today, which was officiated by Prime Minister Datuk Seri Ismail Sabri Yaakob. 

He added that various vacancies in management and non-management fields would be filled, besides assuring that local manpower requirements would increase to 70% of the quota by 2023, in line with the progress of the project.

Touching on the progress of the Genting Tunnel project, Wee said the installation of the first tunnel boring machine (TBM1) was completed for pilot testing in April 2022.

The Genting Tunnel is the first ECRL tunnel to be excavated using the TBM method as opposed to the drilling and blasting method that has been used for other tunnels so far.

The cost of the ECRL Project involving 59 tunnels is estimated to reach RM50.27 billion and includes construction work in four states, namely Kelantan, Terengganu, Pahang and Selangor. – Bernama, June 23, 2022

Related News

Malaysia / 3w

Pahang hospitals test drones to deliver blood samples

Malaysia / 3w

Cabinet approves 17 measures to beef up KLIA security checks, controls

Malaysia / 3w

Pahang police reject claims of drug cartel operating in Genting Highlands

Opinion / 1mth

Orang Asli in Pahang: Token gestures or genuine recognition?

Malaysia / 4mth

Private Amirul's death: Police have called 16 witnesses

Malaysia / 5mth

Be patient, exercise caution when driving home for Aidilfitri - Pahang Sultan

Spotlight

Malaysia

Wanita UMNO: Najib’s contributions must not be erased, says Noraini

Malaysia

Guan Eng hands recommendations to PM to boost unity, integrity between West, East Malaysia.

By Ian McIntyre

World

Five dead, 87 missing after ferry fire off Palawan

Malaysia

Anwar surprised by Najib's new pardon attempt

Malaysia

Lawyer denies Abdul Azeez chose to appear in lock-up uniform, handcuffs

Malaysia

Flying Doctor Service to continue despite fatal Sarawak crash

Opinion

“I’m not a war criminal, I’m a patriot”: Shavendra Silva’s amnesia tour meets the receipts

By Abbi Kanthasamy

Malaysia

British management on trial – does a royal management institute deliver value?

Malaysia

Nearly 10,000 potential fire hotspots detected on RSPO-managed land

You may be interested

Malaysia

No one forced Azeez to wear lock-up attire, handcuffs, says MACC

Malaysia

PM deeply moved remembering Zainol Afiq flying him during GE15 (video)

Malaysia

Abdul Azeez, 2 former TH officials remanded for 2 days

Malaysia

PPIM calls for asset seizures, harsher penalties for scam syndicates

Malaysia

Abdul Azeez claims trial over RM193.5m Tabung Haji investment

Malaysia

Serian air quality remains very unhealthy as haze spreads

Malaysia

Northern Malaysia must prepare for the consequences of lower rainfall

Malaysia

Sarawak FDS fatal helicopter crash had airworthiness certificate until 2027 - CAAM