JB-Singapore RTS Link to reach 70% progress by Dec 2023: exco

It is expected to begin operations in 2027

Updated 4 years ago · Published on 22 Jun 2022 2:54PM

JB-Singapore RTS Link to reach 70% progress by Dec 2023: exco
The RTS line is a 4km cross-border railway project connecting the terminal in Singapore at Woodlands North station to the Malaysian terminal at Bukit Chagar, Johor Baru. – Land Transport Authority pic, June 22, 2022

ISKANDAR PUTERI – The Johor government is targeting to reach 70% progress with the Johor Baru-Singapore Rapid Transit System (RTS) Link by December next year.

State Works, Transport and Infrastructure Committee chairman Mohamad Fazli Mohamad Salleh said work on the customs, immigration, and quarantine complex were expected to reach 50% in the same period.

“As of May 30, the project is at 17%. The RTS Link project is scheduled to be fully completed by December 2026 and will begin operations on January 1, 2027,” he said during the second meeting of the first session of the 15th Johor assembly at the Sultan Ismail Building here today.

 He was replying to a question from Chen Kah Eng (Stulang-PH) on the development status of RTS construction in the state.

Fazli said the state government is now in the planning stage of establishing a Public Transport Integration Committee in Johor Baru to plan the movement of passengers using the RTS.

“Among the systems that will be integrated are the bus system – comprising the Bus Muafakat Johor service and commercial buses – the Iskandar Rapid Transit system, the Gemas-Johor Baru Electric Double Track Project, and the proposed Johor Bahru LRT development.

“The Johor Baru City Council (MBJB) ) is also planning to develop a centralised car park at Plaza Seni and Danga City Mall,” he said. 

The RTS line is a 4km cross-border railway project connecting the terminal in Singapore at Woodlands North station to the Malaysian terminal at Bukit Chagar, Johor Baru.

Once completed, the RTS network will be able to carry 10,000 passengers per hour in each direction. 

Meanwhile, when met outside the state assembly, Fazli said the state government had agreed to conduct a feasibility study for LRT services in the city.

“The LRT services will involve the governance of local authorities such as MBJB, Iskandar Puteri City Council, Pasir Gudang City Council, and Kulai Municipal Council,” he said. – Bernama, June 22, 2022

Related News

Malaysia / 2y

RTS Link connecting span completed, marking new bond of travel for M'sians, S'poreans

Malaysia / 3y

JB-Singapore RTS Link almost 33% done: exco

Malaysia / 3y

MoT, Johor agree to prioritise JB-S’pore RTS link

Malaysia / 4y

SG-JB shuttle link 17% complete: transport minister

Spotlight

Opinion

Can Najib break Madani?

World

Trump offers UFC CEO the position of Press Secretary

Malaysia

Building a great nation begins with happy families, says Anwar

Malaysia

Anwar should sack BN ministers who are not aligned with him – Muhyiddin

Malaysia

AGC rejects claims of defying King’s decree on Najib

Malaysia

Deepavali: Selangor Sultan calls on Malaysians to strengthen unity, reject hatred

Malaysia

If there were still obstacles, why accept the RM50m payment, asks Najib’s daughter

Malaysia

Where did UMNO's RM50 million payment for Najib's release come from?

By The Vibes Says

You may be interested

Malaysia

Rosmah says she knows nothing about RM50m fine related to Najib’s house arrest

Malaysia

Anthony Loke’s resignation takes effect when Najib arrives home

By Alfian Z.M. Tahir

Malaysia

Building a great nation begins with happy families, says Anwar

Malaysia

Prepare a 72-hour food supply; avoid panic buying – FOMCA

Malaysia

Little activity at Najib’s Langgak Duta home as house arrest remains uncertain

Malaysia

PLUS highway congested since midnight ahead of Deepavali

Malaysia

Bersatu takes swipe at PAS over two-seat contest in Melaka polls

By Alfian Z.M. Tahir

Malaysia

Selangor rolls out 105 flood mitigation projects worth RM4.28b amid renewed flooding